The whole project
Systematic completion is a process for the whole project, from idea to operation. The tests at the end confirm a plan that was made early.
Resources
Systematic completion and operational readiness start in the early phase and follow the project all the way. First, how the building must work in operation is described. The tests at the end show that it works, and the organisation is ready to take it into use.
In brief
Systematic completion is a process for the whole project, from the first idea to a building that works in operation.
In advanced buildings such as hospitals, laboratories and airports, the technical installations are tightly linked, like a machine. Ventilation needs power, heating, cooling and automation before it can start, and the nurse call system has to work in every single room. Each of these requirements is set in the early phase and followed all the way to the test that shows it works.
The requirements you set at the start decide what you can test and hand over at the end. Decisions in the early phase cost the least and add the most value. That is why systematic completion is there from the first line drawn, and the tests at the end confirm a plan everyone has worked to.
The operational readiness project is the organisation's own project for taking the building into use. It starts in the concept phase, runs side by side with the construction project and prepares the organisation with work processes, operations and skills. The Norwegian guidance for the early phase of hospital building projects recommends setting it up as early as possible.
Throughout the project
Systematic completion and operational readiness run side by side through every phase. Most of the work happens long before the tests on site.
The essentials
Systematic completion is a process for the whole project, from idea to operation. The tests at the end confirm a plan that was made early.
Start with what the building must be in operation, before choosing equipment and drawing. The requirements at the start decide what can be tested at the end.
Decisions in the early phase cost the least and add the most value. What is settled on paper is solved before it reaches the jobsite.
Zones and dependencies are mapped during design, so the building can be completed and tested area by area.
Users and the operations organisation are involved from the first day, and operational readiness is planned together with completion.
Step by step
In the early phase, the client, users and operations describe what the building must do. The requirements become the basis for the system list, the functional descriptions and the tests.
Installations are mounted in takt, area by area, with self-inspection before the zone is released to the next trade. Testing and start-up have their own place in the takt plan.
When the areas are finished, the work is managed by system. Dependencies set the order: ventilation starts when power, heating, cooling and automation are ready.
Integrated tests and full-scale tests show that the systems work together, with clear milestones up to the building being taken into use.
The organisation runs an ordinary day in the building before the first users arrive, and adjustments are made while they are easy.
Operational readiness
Operational readiness matures the organisation along three tracks, in parallel with the phases of the construction project. The better the tracks are described early, the better the rooms, functions and systems.
Skills, staffing, roles and new work processes are built up step by step through the whole project, with systematic training from the construction phase.
Technical operations and support services are mapped early, requirements for operating agreements go into the contracts, and the operations organisation knows what to do the day the building is taken into use.
The benefits and the target picture set the direction for how the organisation will run in the new building, with new systems and work processes from day one.
Questions and answers
In the early phase. That is where the requirements and functions for the building in operation are described, and the completion strategy is set. The completion plan and zoning come in the preliminary design, test matrices and ITB coordination in the detailed design. International frameworks such as ASHRAE Guideline 0 and CIBSE Commissioning Code M also start with the owner's requirements before design.
In the concept phase, at the same time as the construction project. The Norwegian guidance for the early phase of hospital building projects recommends that the health trust sets up the operational readiness project as early as possible, and that the preliminary design includes a complete benefits realisation plan.
A structured, management-led process that ensures the project meets all functional requirements within time, cost and quality, from planning to handover. The definition comes from the Norwegian BA2015 programme.
The organisation that will take the building into use, with the top manager as owner. Operational readiness is responsible for involving users and staff, and works closely with the construction project through one shared plan.
The plan for how the project will be completed: milestones, zones, systems, tests, responsibilities and documentation. It is made in the preliminary design and carried into the contracts, so all parties work towards the same requirements.
Start-up gets each system running and balanced on its own. Commissioning connects the systems and shows that they work as a whole, with integrated tests and full-scale tests.
ITB is the Norwegian abbreviation for integrated technical building installations: technical systems that depend on each other, such as ventilation, automation, access control and fire alarms. The standard NS 3935 describes how ITB is handled from design to handover, and ITB tests show that the interplay works.
A test where the whole building, or large parts of it, faces a real event, such as a power failure or a fire alarm. The test shows that all the systems respond correctly together.
A dress rehearsal where the staff run an ordinary day in the building before opening, with work processes, equipment and systems in use. The test shows that the organisation and the building work together.
Installation follows the location: the trades move zone by zone, so the work flows. Testing and commissioning follow the system, because a ventilation system runs through the whole building and needs power, heating, cooling and automation. That is why the plan shifts from area to system towards the end.
Fewer surprises in the closeout, an orderly handover and a building that works from day one. A large study from Lawrence Berkeley National Laboratory found median energy savings of 13 percent in new buildings with systematic commissioning, at a cost of 0.4 percent of the construction cost.
Yes. Town halls, schools, universities, laboratories and airports have the same need: the organisation will adopt new systems, routines and roles. Airports call it ORAT, and the UK uses Soft Landings. Both start in the early phase.
Sources
Start for free

Methods for planning and carrying out completion on the jobsite in a structured way. The course is in Norwegian.
Start the course
A smooth, structured transition when a building or facility passes from construction to operations. The course is in Norwegian.